Installation
Handling Existing Lightning Protection During Metal Roof Replacement
Do not let a roofer disconnect, move, or reinstall an existing lightning‑protection system by assumption; document air terminals, conductors, bonds, ground connections, penetrations, and records, and have a qualified lightning‑protection professional coordinate removal, protection, storage, reinstallation, redesign, and inspections.
What factors determine how to handle existing lightning protection?
- Existing system documentation
- Find the original layout, installer, inspection records, and rooftop-change notes. Missing records increase the need for qualified review before reuse[1][3].
- Who controls removal and reinstallation
- Roofing and lightning protection are separate scopes. Identify the qualified lightning contractor responsible for disconnection, storage, reinstallation, bonding, and records[1][3].
- Penetrations and attachment compatibility
- Attachments or penetrations must follow roof-covering and edge-system instructions for compatible brackets, fasteners, adhesives, and flashing[4][5].
- Changes to the roof landscape
- New vents, HVAC equipment, skylights, antennas, cameras, or changed geometry can alter bonding and termination needs[1]. The exact roof system, site conditions, and controlling written documents should be reviewed before work begins[1].
- Inspection and local approval
- Ask the AHJ about permits, inspections, records, and close-out documentation. Inspection options do not make this home compliant[1][3][5].
| Existing component | Why it matters to reroofing | Party that must verify it | Record to retain |
|---|---|---|---|
| Air terminals/conductors | Removal changes layout and attachment points[1]. | Lightning professional | Photos, plan, scope |
| Penetrations/bonds | Flashing must preserve weatherproofing and bonding[1][5]. | Lightning and roofing professionals | Compatible detail |
| Grounding/down conductors | Work may damage or disconnect the path to ground[1][2]. | Lightning professional; AHJ if required | Before/after records |
| Rooftop equipment | Changed metalwork may require bonding or revised termination[1]. | Lightning professional and affected trade | Updated component list |
| Situation | Coordination path | Decision status |
|---|---|---|
| Records/details available | Document removal, protect components, reinstall under the specialist, and inspect[1][4]. | May proceed |
| Roof or equipment changes | Obtain a revised detail before removal[1][5]. | Redesign first |
| Unknown condition/approval | Pause until assessment, responsibilities, records, and inspection steps are written[1][3][5]. | Postpone |
What records, duties, and steps should homeowners & contractors follow?
It uses LPI, NFPA 780, metal-construction guidance, 2024 IBC integration language, and UL 96A[1][2][3][4][5][6].
When metal makes sense
- A written lightning-protection scope covers sequencing and responsibilities[1].
- The manufacturer documents compatible attachment, penetration, flashing, and material details[4][5].
- Records, photos, and inspection path are assembled before work[1][3].
When it is not recommended
- Do not proceed without a qualified lightning professional's written removal/reinstallation scope[1][3].
- Postpone when damage or missing records leave assessment and inspection responsibility unresolved[1].
- Do not use an attachment approach while manufacturer or AHJ direction is unknown[5].
- Metal may not fit the schedule if redesign or inspection cannot be completed first.
General coordination information, not electrical, engineering, legal, insurance, or code-compliance advice. Do not alter the system yourself; confirm current requirements with the AHJ, roofing manufacturer, and qualified lightning professional.